Project scope consists of roadway paving, storm sewer repairs, new water main and parkway restoration. The project improvements include:

· All new asphalt pavement
· Storm sewer repairs
· Water main replacement and upsizing with new homeowner water services
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
September 2013 – End of Construction



Friday, June 28, 2013

Underground Utilities Complete on Woodmere

Woodmere Lane: Last week the contractor completed the abandonment of the existing water main at Glenview Road and completed some miscellaneous structure adjustments and tasks around the jobsite. A leakage test on the newly installed water main was also completed.

The contractor has a few items to complete prior to being done on Woodmere Lane including site clean-up, grading of lawns, and minor repairs. At this time, the lawns will be graded in preparation for sod; however, sod will not be installed until the Fall when growing conditions are more favorable. 

Currently, the contractor will not be working on Thursday, July 4th and is not scheduled to be working on-site on Friday, July 5th.

Once the underground work is 100% completed, the entire roadway will be paved as part of the Village’s 2013 Street Resurfacing Project.

Locust Lane: No work is anticipated. 

Thank you for your patience during the construction operations.

Monday, June 24, 2013

Woodmere Water Shut-Down on June 25th.

A water main shut-down is scheduled from Woodmere Lane from Glenview Road to the south end. This water shut-down is needed so the existing water main can be disconnected at Glenview Road.

The shut down is scheduled from 9:00 AM to 1:00 PM on Tuesday, June 25th.

Friday, June 21, 2013

Trench Paving on Woodmere Completed

Woodmere Lane: Last week the contractor completed the asphalt trench paving within the stone trenches created during the underground utility improvements. The contractor also performed the internal epoxy lining of the existing sanitary sewer manholes.

The contractor has a few miscellaneous items to complete prior to being done on Woodmere Lane including abandoning the existing water main at Glenview Road, structure adjustments, site clean-up, and a few minor repairs.

Once the underground work is 100% completed, the entire roadway will be paved as part of the Village’s 2013 Street Resurfacing Project.

The water main abandonment will require a water main shut down. Residents will be notified 24-hours prior to water being turned off.

Locust Lane: No work is anticipated. 

Thank you for your patience during the construction operations.

Tuesday, June 18, 2013

Trench Paving Postponed

Yesterday a post was created stating that trench paving was going to begin today (Tuesday, June 18th). We got late notice that this work is now postponed to Wednesday, June 19th.

There might be some work on-site in preparation for the trench paving, but the work has been postponed.

Sorry for any inconvenience this has caused. We will keep you posted of any future updates.

Monday, June 17, 2013

Trench Paving on Woodmere on June 18th.

Woodmere Lane Residents -
We received late notice from the contractor that they will begin asphalt paving the stone trenches starting tomorrow, Tuesday, June 18th.

We ask for additional patience during these operations. Getting by all of the construction equipment will be difficult. We would ask that you minimize any trips to and from your homes as much as possible during working hours.

Thank you again for your patience. It will be well worth it to minimize the amount the dust in the neighborhood.

Friday, June 14, 2013

Woodmere Underground Utilities Nearly Complete

Woodmere Lane: Last week the contractor complete installing the water services to each home. The contractor also completed some miscellaneous underground utilities improvements to the storm and sanitary sewer system.

Work remaining includes epoxy lining of sanitary sewers, abandoning the existing water main, and trench paving. Trench paving is scheduled to be completed in the next few weeks. The Village is committed to  ensuring the open stone trenches are properly maintained until the asphalt pavement can be installed.

The water main abandonment will require a water main shut down. Residents will be notified 24-hours prior to water being turned off.

Locust Lane: No work is anticipated. 

Thank you for your patience during the construction operations.

Friday, June 7, 2013

Water Services Continue on Woodmere

Woodmere Lane: The contractor completed the storm sewer installation last week and began installing water services to individual homes.

Next week the contractor will complete the water service installation to each resident and perform some miscellaneous underground utility work.

During water service installation and connection to the existing service, water to individual homes will be shut off for a short period of time. The contractor will knock on the door of any home that will not have water prior to turning it off.

Locust Lane: No work is anticipated. 

Thank you for your patience during the construction operations.