Woodmere Lane:
No work completed on-site last week.
The final step in completing the project will be the installation of sod. Depending on the weather conditions, the contractor may begin installing sod. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions.
Locust Lane:
Last week the contractor performed work in preparation for asphalt paving including grading of the existing aggregate base course, repairing unstable sections of the base course, and saw-cutting of intersections and driveways. The contractor also installed the asphalt binder layer on the roadway.
Next week, the contractor is scheduled to perform landscape grading, topsoil installation, leakage testing, and other miscellaneous tasks. Depending on the weather conditions, the contractor may begin installing sod. Otherwise, the contractor will wait until the weather is cooler for more favorable growing conditions.
Once the landscape restoration is completed, the asphalt surface layer will be installed.